VINE TRAIL UPDATE 02/08/16 - 02/12/16

 

VINE TRAIL - Oak Knoll Section

- Installation of block wall for trail grading at the south end of the Dry Creek Bridge

- RM Harris installing joint sealer at Hinman Bridge GBI installing cross drains along trail

- RM Harris installing new railings at Dry Creek Bridge

- GBI making subgrade and compacting aggregate base in Yountville across from the Vintners Golf Course.

 

Installation of block wall for trail grading at the south end of the Dry Creek Bridge

 