2019, Andrea Ave, City of St. Helena

  • Project #:
    19541
  • Est. Start Date:
    2019
  • Est. Completion Date:
    Oct 2020
  • Beginning Location:
    Kearney St
  • End Location:
    Oak Ave
  • Section Length:
    410'
  • Map Cordinates:
    38.506088, -122.475064
  • Description of Improvements:

    Curb Ramps, 2″ AC Overlay with Fabric, Striping on Andrea Ave from Kearney St to Oak Ave

  • Total Project Cost
    $ 62,436
  • Spent
    $ 2,660
Phase
  • Design
  • Construction
  • Complete