Project #: 19538
Est. Start Date: 2018
Est. Completion Date: Dec 2018
Beginning Location: El Bonita Ave
End Location: end of El Bonita Cir
Section Length: 120'
Map Cordinates: 38.493813, -122.459061
Description of Improvements:

Curb Ramps, 2.5" AC Overlay with Fabric, Striping on El Bonita Cir from El Bonita Ave to end of El Bonita Cir

Total Project Cost

$71,980

Phase
  • Design

  • Construction

  • Complete