close
BACK

2019, Marshall Ave, Napa County

  • Project #:
    19512
  • Est. Start Date:
    2019
  • Est. Completion Date:
    Oct 2019
  • Beginning Location:
    2172 Marshall Ave
  • End Location:
    Imola Ave
  • Section Length:
    426'
  • Map Cordinates:
    38.281222, -122.266392
  • Description of Improvements:

    Road Reconstruction and Overlay on Marshall Ave from 2172 Marshall Ave to Imola Ave (up to Napa City limit)

  • Total Project Cost
    $122,389
  • Spent
    113,531
Phase
  • Design
  • Construction
  • Complete