2020, Milton Road Phase 2, Napa County

  • Project #:
    20512
  • Est. Start Date:
    2020
  • Est. Completion Date:
    Oct-20
  • Beginning Location:
    2,700 ft south of Las Amigas
  • End Location:
    End of road
  • Section Length:
    12,700'
  • Map Cordinates:
    38.224030, -122.317900
  • Description of Improvements:

    Overlay on Milton Road, 2,700 ft south of Las Amigas to End.

  • Total Project Cost
    $893,510
  • Spent
    868,184
Phase
  • Design
  • Construction
  • Complete