close
BACK

2019, Trower Ave Phase 2, City of Napa

  • Project #:
    19573
  • Est. Start Date:
    2019
  • Est. Completion Date:
    Nov 2020
  • Beginning Location:
    Linda Vista Ave
  • End Location:
    Dry Creek Rd
  • Section Length:
    2,700'
  • Map Cordinates:
    38.325144, -122.327724
  • Description of Improvements:

    Hot Mix Asphalt Grind and Overlay and Concrete Improvements on Trower Ave from Dry Creek Rd to Linda Vista Ave; Hot Mix Asphalt Grind and Overlay with Concrete Curbs, Gutters, Sidewalks and Curb Ramps on Trower Ave from Jefferson St to East End (City Limits); Overlay on Jefferson St from Trower Ave to Sierra Ave.

  • Total Project Cost
    $2,000,000
  • Spent
    $1,858,291
Phase
  • Design
  • Construction
  • Complete