2019, Trower Ave Phase 2, City of Napa

Project #: 19573
Est. Start Date: 2019
Est. Completion Date: Nov 2019
Beginning Location: Linda Vista Ave
End Location: Dry Creek Rd
Section Length: 6,400'
Map Cordinates: 38.325144, -122.327724
Description of Improvements:

Hot Mix Asphalt Grind and Overlay and Concrete Improvements on Trower Ave from Dry Creek Rd to Linda Vista Ave;  Hot Mix Asphalt Grind and Overlay with Concrete Curbs, Gutters, Sidewalks and Curb Ramps on Trower Ave from Jefferson St to East End (City Limits).
 

Total Project Cost

$2,029,037

Phase
  • Design

  • Construction

  • Complete

Location Image

Location