VINE TRAIL UPDATE 10-26-15 – 10-30-15

10/26/15 - 10/30/15 UPDATE:

VINE TRAIL - Oak Knoll Section 

 

- Ghilotti Bros. working on installing block, between Oak Knoll Ave. & Luke Dr.
 
- Ghilotti Bros. grading and compacting subgrade and aggregate base Wine Country Ave. to Luke Dr.
 
- Atlas Tree working along Solano Ave, between California & Hoffman.
 
- RM Harris stripping formwork and false work on Dry Creek Bridge.
 
- RM Harris at new Hinman Bridge pouring footings next to Solano Ave.
 

CLICK HERE to read more about the VINE TRAIL.

 

Installing new block and backfilling with drain rock between Oak Knoll to Luke