19568 |
2019 |
City of St. Helena |
Hudson Ave |
Overlay on Hudson Ave from Adams St to Spring St |
$62,308 |
$57,216 |
$5,092 |
Mar 2019 |
Oct 2020 |
19520 |
2019 |
City of American Canyon |
American Canyon Rd East |
Overlay on American Canyon Rd East from SR-29 to Bridge |
$190,773 |
$165,042 |
over budget |
Jun 2019 |
Mar 2020 |
19569 |
2019 |
City of St. Helena |
Money Way |
Overlay on Money Way from Adams St to Spring St |
$35,081 |
$32,214 |
$2,867 |
Mar 2019 |
Oct 2020 |
19521 |
2019 |
City of American Canyon |
American Canyon Rd East |
Mill and Overlay on American Canyon Road East from Bridge to Flosden Intersection |
$551,123 |
$427,918 |
over budget |
Jun 2019 |
Mar 2020 |
19570 |
2019 |
City of St. Helena |
Paulson Ct |
Overlay on Paulson Ct from Pope St to end of Paulson Ct N |
$31,070 |
$28,531 |
$2,539 |
Mar 2019 |
Oct 2020 |
19522 |
2019 |
City of American Canyon |
American Canyon Rd East III |
Mill and Overlay on American Canyon Rd East at the Flosden Intersection |
$52,993 |
$43,412 |
over budget |
Jun 2019 |
Mar 2020 |
19523 |
2019 |
City of American Canyon |
Arden Ct |
Mill and Overlay on Arden Ct from Knightsbridge Way to end of Arden Ct |
$17,864 |
$17,864 |
0 |
Jun 2019 |
Apr 2020 |
19505 |
2019 |
Napa County |
Coronado Ave |
Road Reconstruction and Overlay on Coronado Ave (up to Napa City limit) |
$93,012 |
$93,012 |
0 |
Jul 2019 |
Oct 2019 |
19526 |
2019 |
City of American Canyon |
Knightsbridge Way |
Mill and Overlay on Knightsbridge Way from Elliott Dr to Danrose Dr |
$99,638 |
$99,638 |
0 |
Jun 2019 |
Jun 2020 |
19506 |
2019 |
Napa County |
London Way |
Road Reconstruction and Overlay on London Way from Coronado Ave to Napa City limit |
$395,299 |
$395,299 |
0 |
Jul 2019 |
Oct 2019 |
19541 |
2019 |
City of St. Helena |
Andrea Ave |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Andrea Ave from Kearney St to Oak Ave |
$39,141 |
$35,942 |
$3,199 |
Mar 2019 |
Oct 2020 |
19527 |
2019 |
City of American Canyon |
Lansford Ct |
Mill and Overlay on Lansford Ct from Knightsbridge Way to end of Lansford Ct |
$21,450 |
$21,450 |
0 |
Jun 2019 |
Jun 2020 |
19507 |
2019 |
Napa County |
Republic Ave |
Road Reconstruction and Overlay on Republic Ave from Coronado Av to Napa City limit |
$116,265 |
$116,265 |
0 |
Jul 2019 |
Oct 2019 |
19542 |
2019 |
City of St. Helena |
Grove Ct |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Grove Ct from Hunt Ave to end of Grove Ct N |
$152,548 |
$140,081 |
$12,467 |
Mar 2019 |
Oct 2020 |
19528 |
2019 |
City of American Canyon |
Linwood Ln |
Mill and Overlay on Linwood Ln from Knightsbridge Way to end of Linwood Ln |
$17,864 |
$17,864 |
0 |
Jun 2019 |
Jun 2020 |
19508 |
2019 |
Napa County |
Holmes Ave |
Road Reconstruction and Overlay on Holmes Ave from 124 Holmes Ave to Shetler Ave (up to Napa City limit) |
$162,770 |
$162,770 |
0 |
Jul 2019 |
Oct 2019 |
19543 |
2019 |
City of St. Helena |
Kearney St |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Kearney St from Hillview Pl to Madrona St |
$51,551 |
$47,338 |
$4,213 |
Mar 2019 |
Oct 2020 |
19529 |
2019 |
City of American Canyon |
Northampton Dr |
Mill and Overlay on Northampton Dr from Elliott Dr to Danrose Dr |
$134,365 |
$134,365 |
0 |
Jun 2019 |
Jun 2020 |
19509 |
2019 |
Napa County |
Shetler Ave |
Road Reconstruction and Overlay on Shetler Ave from 1082 Shetler Ave to 1090 Shetler Ave (up to Napa City limit) |
$139,517 |
$139,517 |
0 |
Jul 2019 |
Oct 2019 |
19544 |
2019 |
City of St. Helena |
Kearney St |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Kearney St from Madrona Ave to Pine St |
$35,323 |
$32,436 |
$2,887 |
Mar 2019 |
Oct 2020 |
19530 |
2019 |
City of American Canyon |
Park Ln |
Mill and Overlay on Park Ln from Knightsbridge Way to end of Park Ln |
$17,864 |
$17,864 |
0 |
Jun 2019 |
Jun 2020 |
19510 |
2019 |
Napa County |
Shetler Ave |
Road Reconstruction and Overlay on Shetler Ave from 1138 Shetler Ave to 1161 Shetler Ave (up to Napa City limit) |
$209,276 |
$209,276 |
0 |
Jul 2019 |
Oct 2019 |
19545 |
2019 |
City of St. Helena |
Spring St |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Spring St from Chardonnay Way to Sylvaner Ave E |
$215,080 |
$197,502 |
$17,578 |
Mar 2019 |
Oct 2020 |
19531 |
2019 |
City of American Canyon |
Regent Ct |
Mill and Overlay on Regent Ct from Knightsbridge Way to end of Regent Ct |
$21,383 |
$21,383 |
0 |
Jun 2019 |
Jun 2020 |
19511 |
2019 |
Napa County |
Whitney Ave |
Road Reconstruction and Overlay on Whitney Ave from Coronado Ave to Marshall Ave |
$162,770 |
$162,770 |
0 |
Jul 2019 |
Oct 2019 |
19546 |
2019 |
City of St. Helena |
Spring St |
Curb Ramps, 2" AC Overlay with Fabric, Striping on Spring St from Sylvaner Ave to Valley View St |
$129,164 |
$118,608 |
$10,556 |
Mar 2019 |
Oct 2020 |
19532 |
2019 |
City of American Canyon |
Strand Ct |
Mill and Overlay on Strand Ct from Knightsbridge Way to end of Strand Ct |
$17,864 |
$17,864 |
0 |
Jun 2019 |
Jun 2020 |
19512 |
2019 |
Napa County |
Marshall Ave |
Road Reconstruction and Overlay on Marshall Ave from 2172 Marshall Ave to Imola Ave (up to Napa City limit) |
$139,517 |
$139,517 |
0 |
Jul 2019 |
Oct 2019 |
19547 |
2019 |
City of St. Helena |
Spring St |
Curb Ramps, 2" AC Overlay, Striping on Spring St from City Limits to 639' W/O Sylvaner Ave |
$125,231 |
$114,996 |
$10,235 |
Mar 2019 |
Oct 2020 |
19513 |
2019 |
Napa County |
Parrish Rd |
Road Reconstruction and Overlay on Parrish Rd from Shetler Ave to Imola Ave |
$232,529 |
$232,529 |
0 |
Jul 2019 |
Oct 2019 |
19548 |
2019 |
City of St. Helena |
Monte Vista Ave |
Curb Ramps, 2.5" AC Overlay with Fabric, Striping on Monte Vista Ave from Hunt Ave to end of Monte Vista Ave N |
$158,577 |
$145,618 |
$12,959 |
Mar 2019 |
Oct 2020 |
19514 |
2019 |
Napa County |
Mayfair Dr |
Road Reconstruction and Overlay on Mayfair Dr from London Way to Shetler Ave |
$209,276 |
$209,276 |
0 |
Jul 2019 |
Oct 2019 |
19549 |
2019 |
City of St. Helena |
Hwy29 / Main St |
Sidewalk improvements: Concrete work on Hwy29 aka Main St from Mitchell Dr to Pine St |
$1,862,500 |
$175,000 |
$1,687,500 |
Feb 2019 |
Jun 2021 |
19583 |
2019 |
City of Calistoga |
Spring St |
Pavement Rehabilitation on Spring St from Cedar St to end. |
$244,113 |
$203,819 |
$40,294 |
Oct 2018 |
Jun 2019 |
19515 |
2019 |
Napa County |
Penny Ln |
Road Reconstruction and Overlay on Penny Ln from Imola Ave to end of Penny Ln |
$465,058 |
$465,058 |
0 |
Jul 2019 |
Oct 2019 |
19550 |
2019 |
City of St. Helena |
Hunt Ave |
Curb Gutter and Ramps, Sidewalks on Hunt Ave from June Ln to Monte Vista Ave |
$302,830 |
$231,980 |
$75,000 |
Jan 2019 |
Mar 2020 |
19517 |
2019 |
Napa County |
Sunnyhill Dr |
Storm Damage Repair and Road Reconstruction on section of Sunnyhill Dr (Circle Oaks) |
$1,101,743 |
$778,150 |
$323,593 |
Jul 2019 |
Oct 2020 |
19552 |
2019 |
City of St. Helena |
Vorhees Cir |
Overlay on Vorhees Cir from Mitchell Dr E to Mitchell Dr W |
$87,351 |
$80,212 |
$7,139 |
Mar 2019 |
Oct 2020 |
19518 |
2019 |
Napa County |
Ridgecrest Dr |
Storm Damage Repair and Road Reconstruction on section of Ridgecrest Dr (Circle Oaks) |
$1,271,803 |
$1,017,657 |
$254,146 |
Jul 2019 |
Oct 2020 |
19553 |
2019 |
City of St. Helena |
Brown St |
Overlay on Brown St from Allison Ave to end of Brown St W |
$46,779 |
$42,956 |
$3,823 |
Mar 2019 |
Oct 2020 |
19584 |
2019 |
City of Calistoga |
Washington St |
Sidewalk work in the north half sector A on Washington St. |
$37,700 |
$37,700 |
0 |
Jun 2019 |
Jul 2019 |
19575 |
2019 |
Napa County |
Berryessa Knoxville Rd at MPM 20.5-22 |
Storm Damage Repair and Road Reconstruction on Berryessa Knoxville Rd to 25' Bridge Span at mile-post-marker 20.5 to mile-post-marker 22 |
$201,314 |
$130,700 |
$70,614 |
Feb 2019 |
Dec 2020 |
19554 |
2019 |
City of St. Helena |
Crinella Ct |
Overlay on Crinella Ct from Main St to Park St |
$32,459 |
$29,806 |
$2,653 |
Mar 2019 |
Oct 2020 |
19576 |
2019 |
Napa County |
Dry Creek Rd at MPM 7.75 |
Storm Damage Repair and Road Reconstruction on Dry Creek Rd at mile-post-marker 7.75 |
$141,665 |
$100,550 |
$41,115 |
Feb 2019 |
Aug 2020 |
19555 |
2019 |
City of St. Helena |
Crinella Dr |
Overlay on Crinella Dr from Park St to the pump station |
$73,985 |
$67,939 |
$6,046 |
Mar 2019 |
Oct 2020 |
19577 |
2019 |
Napa County |
Dry Creek Rd at MPM 10.5 |
Storm Damage Repair and Road Reconstruction on Dry Creek Rd at mile-post-marker 10.5 |
$139,952 |
$98,250 |
$41,702 |
Feb 2019 |
Aug 2020 |
19556 |
2019 |
City of St. Helena |
Crinella Dr |
Overlay on Crinella Dr from the pump station to Park St |
$70,645 |
$64,872 |
$5,773 |
Mar 2019 |
Sep 2020 |
19572 |
2019 |
City of Napa |
Trancas St Phase 1 |
HMA Overlay, Curb, Gutter, Sidewalk and Curb Ramps, Traffic Signals on Trancas St from Hwy 29 to Jefferson St |
$1,500,000 |
$1,500,000 |
0 |
Aug 2019 |
Nov 2020 |
19578 |
2019 |
Napa County |
Dry Creek Rd at MPM 10.75 |
Storm Damage Repair and Road Reconstruction on Dry Creek Rd at mile-post-marker 10.75 |
$182,517 |
$129,300 |
$182,517 |
Feb 2019 |
Oct 2021 |
19557 |
2019 |
City of St. Helena |
Park St |
Overlay on Park St from Pratt Ave to Crinella Dr |
$53,270 |
$48,916 |
$4,354 |
Mar 2019 |
Sep 2020 |
19579 |
2019 |
Napa County |
Mt Veeder Rd at MPM 4.75 |
Storm Damage Repair and Road Reconstruction on Mt Veeder Rd at mile-post-marker 4.75 |
$182,517 |
$129,300 |
$53,217 |
Feb 2019 |
Aug 2020 |
19558 |
2019 |
City of St. Helena |
Park St |
Overlay on Park St from Christine Ct to Crinella Dr |
$42,483 |
$39,011 |
$3,472 |
Mar 2019 |
Sep 2020 |
19574 |
2019 |
City of Napa |
Lincoln Ave & Main St |
Traffic Signals and Interconnect at Lincoln Ave and Main St Intersection. Traffic signal project. |
$600,000 |
$600,000 |
0 |
Jul 2019 |
Nov 2020 |
19580 |
2019 |
Napa County |
Dry Creek Rd at MPM 7.51 |
Storm Damage Repair and Road Reconstruction on Dry Creek Rd at mile-post-marker 7.51 |
$159,231 |
$116,300 |
$42,931 |
Feb 2019 |
Aug 2020 |
19559 |
2019 |
City of St. Helena |
Christine Ct |
Overlay on Christine Ct from Park St to end of Christine Ct E |
$20,048 |
$18,410 |
$1,638 |
Mar 2019 |
Sep 2020 |
19560 |
2019 |
City of St. Helena |
Henry Ct |
19560Overlay on Henry Ct from Park St to end on Henry Ct E |
$11,456 |
$10,520 |
$936 |
Mar 2019 |
Sep 2020 |
19573 |
2019 |
City of Napa |
Trower Ave Phase 2 |
Hot Mix Asphalt Grind and Overlay and Concrete Improvements on Trower Ave from Dry Creek Rd to Linda Vista Ave; Hot Mix Asphalt Grind and Overlay with Concrete Curbs, Gutters, Sidewalks and Curb Ramps on Trower Ave from Jefferson St to East End (City Limits); Overlay on Jefferson St from Trower Ave to Sierra Ave. |
$2,000,000 |
$2,000,000 |
0 |
Jul 2019 |
Nov 2020 |
19581 |
2019 |
Napa County |
Mt Veeder Rd at MPM 4.0 |
Storm Damage Repair and Road Reconstruction on Mt Veeder Rd at mile-post-marker 4.0 |
$154,363 |
$133,150 |
$21,213 |
Feb 2019 |
Oct 2021 |
19561 |
2019 |
City of St. Helena |
Spring St |
38.492062Overlay on Spring St from Sylvaner Ave W to Chardonnay Way |
$162,629 |
$149,339 |
$13,290 |
Mar 2019 |
Oct 2020 |
19582 |
2019 |
Napa County |
Mt Veeder Rd at MPM 5.1 |
Storm Damage Repair and Road Reconstruction on Mt Veeder Rd at mile-post-marker 5.1 |
$156,641 |
$134,300 |
$22,341 |
Feb 2019 |
Oct 2021 |
19562 |
2019 |
City of St. Helena |
Spring St |
Overlay on Spring St from 639' west of Sylvaner Ave to Sylvaner Ave |
$61,844 |
$56,790 |
$5,054 |
Mar 2019 |
Oct 2020 |
19563 |
2019 |
City of St. Helena |
Kearney St |
Overlay on Kearney St from Pine St to Adams St |
$56,324 |
$51,721 |
$4,603 |
Mar 2019 |
Sep 2020 |
19551 |
2019 |
City of St. Helena |
Volker Ct |
Overlay on Volker Ct from Crinella Dr to end of Volker Ct |
$20,048 |
$18,410 |
$1,638 |
Mar 2019 |
Oct 2020 |
19564 |
2019 |
City of St. Helena |
Arrowhead Dr |
Overlay on Arrowhead Dr from Sulphur Springs Ave to end of Arrowhead Dr S |
$79,210 |
$72,737 |
$6,473 |
Mar 2019 |
Oct 2020 |
19504 |
2019 |
Town of Yountville |
Yount St |
Road Reconstruction and Micro Surface on Yount St from Mount Ave to Finnell Rd |
$368,293 |
$368,293 |
0 |
Apr 2019 |
Jun 2019 |
19565 |
2019 |
City of St. Helena |
McCorkle Ave |
Overlay on McCorkle Ave from Allison Ave to end of McCorkle Ave W |
$17,542 |
$16,109 |
$$1,433 |
Mar 2019 |
Oct 2020 |
19516 |
2019 |
Town of Yountville |
Yount St |
Overlay on Yount St from Finnell Rd to Washington St |
$85,569 |
$85,569 |
0 |
Apr 2019 |
Jun 2019 |
19566 |
2019 |
City of St. Helena |
Church St |
Overlay on Church St from Hunt Ave to Pope St |
$40,322 |
$37,027 |
$3,295 |
Mar 2019 |
Oct 2020 |
20503 |
2019 |
Town of Yountville |
Microsurface treatment Mulberry St area & Adams St area |
Microsurfacing treatment to Mulberry St, Heather St, Holly St and Larkspur St. Microsurfacing treatment to Adams St, Jefferson St, Lande Way, Pedroni St and Stags View Ln |
$157,249 |
$157,249 |
0 |
Oct 2019 |
Nov 2019 |
19504.1 |
2019 |
Town of Yountville |
Yount St storm drain 40' |
Reconstruct storm drain 40' at 6654 Yount St |
$11,036 |
$11,036 |
0 |
Feb 2019 |
Feb 2019 |
19567 |
2019 |
City of St. Helena |
Hudson Ave |
Overlay on Hudson Ave from Madrona Ave to Adams St |
$58,530 |
$53,747 |
$4,783 |
Mar 2019 |
Oct 2020 |